Rift Between City & School District
Audit Latest Imbroglio
The City Council has suggested the School District Board of Trustees audit Turner Construction, the builder of the Emeryville Center of 'Community' Life in order to claw back some money the district might have overpaid for the building project but the Board President is demurring, indicating he is more inclined to try to get money out of its ECCL partner, the City of Emeryville instead. It's part of a growing rift between the District and City Hall born out of differences in how to divide up cost overruns in the contentious schools/community center project.
The City/Schools Committee, consisting of the membership of the City Council and the School Board, met May 4th and the frosty relations were evident when Vice Mayor John Bauters suggested going to construction giant Turner, who has recently been indicted for bilking clients, to see if there may be recoverable costs to help offset the cost overruns of ECCL*. The idea was embraced by the entire Council but Board President Merriam oddly said it would not be appropriate, a position he has held for quite some time even as he has refused to properly elaborate.
Mr Merriam joined with former Board President John Affeldt last summer in quashing an attempt to audit Turner, citing the existence of the Citizens Oversight Committee (COC) makes it unnecessary.
![]() |
| Emery School Board President Donn Merriam 'Even though Turner Construction has been caught overcharging clients, we must not audit them'. |
Just two years ago the County of Santa Clara held Turner to task for cost overruns and delays. Turner blamed the city for the issues.
Mr Merriam's odd assertion of no Turner audit brings into question who's interests he has at heart. The ECCL budget went significantly over budget and is still not complete. Board member Brynnda Collins, when expressing her support for a Turner audit, questioned the quality of the work stating, "Big chunks of metal (are) falling and almost hitting a teacher." There have been multiple suggestions of design flaws like lack of storage, concrete poured too thin and poor drainage.
It is clear to many there are enough reasons for an audit. City Council member Bauters stated it could find enough savings to cover the remaining $370,000 the district owes Turner.
Los Angeles Unified School District routinely audits projects. It should be noted LAUSD is so large that they have a group that audits every project. Turner recently was found to have overcharged them $190,000 on a $98 million project, almost exactly the same size project as ECCL.
Conflict of Interest?
Clearly audits are done and effective tools to protect taxpayer funds. Which leads back to the question, does Board President Merriam have a Turner connection in his work as an employee of the architecture firm of Deems Lewis Mckinley (DLM)? A Tattler search of their projects and Turner's revealed no direct overlap. However it did turn up a project that involved Swinerton Management and DLM. Swinerton worked on the ECCL project and frequently partners with Turner.
South San Francisco Unified passed a large bond project and used Swinerton to manage the project. DLM bid on and was chosen to do the work. It is not clear if the Emery Board President personally worked on the project but the appearance of impropriety is evident. Of course, an elected official should not be in the position to have to chose between what is best for their constituents and their pocketbooks.
The School Board is scheduled to discuss auditing the ECCL project at their May 10th meeting and Mr Merriam should leave the room while this is being discussed. If he stays in the room, he should disclose the firm's relationship with Swinerton and have the legal counsel provide guidance. It should be noted President Merriam has been caught violating simple rules of transparency because he claimed he was unaware of the conflict.
*NOTE: Although Turner Construction is a 'primary partner' with Turner GROUP Construction, it was Turner GROUP Construction that was indicted for bilking it's clients. Turner Construction, the builder of the ECCL wasn't indicted but they were found to be overcharging their clients as the story states. The Tattler apologizes for the mix up.