Tuesday, November 30, 2021

Guest Column: John Fricke on Emeryville's New Bike/Ped Bridge

The Long and Winding Road to the Bay Street Pedestrian/Bicycle Bridge

by John Fricke

Guest Columnist

The pedestrian/bicycle bridge to Bay Street shopping mall will open December 3rd, this Friday evening.  It's been a long time coming.  Formally proposed in Emeryville’s 1993 General Plan, the bridge idea languished until 2002 when the City paid an engineering firm to produce a rough design, which began for me a yearlong effort to torpedo the flawed design, and promote a more functional design.  

By 2003, I had become very familiar with Emeryville’s streets and sidewalks while behind the wheel of a double stroller occupied by my twin daughters.  

Nina Criswell & Lane Fricke
in the Emeryville City
Council chambers

Then (as now), Emeryville city government prioritized the car over pedestrian and bicycle access.  On a typical walk from my house with Lane and Nina in the stroller, we would risk life and limb crossing San Pablo Avenue (or wait an interminable period of time at a traffic signal).  Various routes north (between the railroad tracks and San Pablo) were pleasant enough.  But I heard rumors that there was a place not far to the west with a gorgeous mile-long path along the water.  One need only traverse railroad tracks, and then a ten-lane freeway.  But how to get there on foot?  

The 40th Street bridge, with its four lanes of speeding vehicle traffic, was not the best environment for facilitating a nap.  In 1997, the Emeryville city government had produced at the train station a pedestrian bridge with elevator and stairs, but no ramp. 

 


Prison watch towers in Emeryville?
Setting aside for the moment the neo-prison-watch-tower design and the placing of the elevator doors out of view from the street, the functionality for someone with a stroller (or wheelchair) depended on the whim of the elevator vandals, and the swiftness of the City to repair the broken elevator.  (Suffice it to say that Emeryville city government appears unfamiliar with the US postal service motto.)  Quite a number of times, Nina, Lane, and I would hold our noses going up the elevator on one side, only to be left waiting at the altar for the down elevator to arrive at the other end of the bridge.

Apparently, the folks in Berkeley responsible for designing the I-80 ped-bike bridge took note of the folly of the elevator/stairs design in Emeryville.  Their bridge design was all ramp, no moving parts.  In 2002, five years after Emeryville cut the ribbon at the prison watch tower, the Berkeley bridge over I-80 opened to critical acclaim.  


Berkeley I-80 ped/bike bridge

So what did we, pedestrians and stroller passengers in Emeryville, receive a year later from the high-priced engineers that the City hired to design a second bridge across the RR tracks?  Gentle reader, you can see where this is going.  Incredibly, the city manager was so pleased with the engineers’ elevator-stairs bridge design that he asked the firm to produce a large 3-D physical model of the bridge.  

In Hans Christian Andersen’s folktale, The Emperor’s New Clothes, one small child’s revelation is quickly embraced by the crowd, but the emperor will not acknowledge his error.  He walks more proudly than ever.  So, too, in Emeryville.  At the first City Council meeting on the elevator-stairs bridge design, I stated the obvious flaws in its design, and suggested that the design should model Berkeley’s bridge of gradual, open ramps.  Could we learn from Berkeley’s success?  ‘No’, came the answer from city government.  At the next City Council meeting, the city manager presented an alternate design which eliminated the elevators, but added narrow, steep, stacked ramps with sharp turns, and blind spots.  



2003 City commissioned design by Mark Thomas & Co
I realized that to kill this bad idea would take more than stating the obvious.  I looked up the federal regulations regarding spanning railroad tracks and then went to the Bay Street mall with my 100-foot tape measure.  Lo and behold, it would be possible to replicate the Berkeley Bridge ramps’ five-percent slope with a there-and-back ramp configuration (between mall parking garage and RR tracks), while still providing a generous open-ramp width of ten feet.  On the east side, there was plenty of room for a straight-shot ramp to the bridge span.  I produced very rough sketches of an open, gradual, wide ramp design.

In talking up the alternate design with neighbors, it soon became obvious that my hard-to-read sketches weren’t telling a thousand words.  I needed help.

        .                                  .                                 .  

Look! Up in the sky!  Is it a bird?  Is it a plane?  No, it’s Philip Rostonovitch!  

From: Philip Rostonovich Sent: Wednesday, Jun 4, 2003 10:41 AM PDT To: John Fricke Subject: question about Pedestrian bridge designs

Hello John,

My name is Philip.  I'm on the Triangle Neighborhood mailing list.  

You've probably seen me around the neighborhood - big guy, long hair, beard, backpack.

Anyway, long intro short: I'm aware of the recent proceedings about the 

proposed pedestrian bridge, but I'm unsure of its current status.  My reason 

for asking is that I have some new free time (recently laid off), and I 

might be able to contribute some 3D computer graphic renderings.

Perhaps my skills can be applied in some helpful way to this or future endeavours.

Thanks for your time, John.  Let me know if I can still be of help.

Sincerely,

Philip Rostonovich


Philip and I went to the site to take photos, and then Philip worked his magic:








These renderings of Philip's told a thousand words.  I met with various groups in Emeryville who endorsed this alternative.  I kept adding neighbors to my email distribution list.  

At the next City Council meeting, several neighbors and I spoke up in favor of the gradual ramp design.  But the emperor kept parading around in his new clothes.  Years later, I was told by someone in the room where it happened that the city manager instructed his city staff members to see to it that my design be undermined.  I was invited to a meeting at city hall with the city engineer, the chief building inspector, and the city’s building code compliance consultant.  Each in turn raised technical objections to my proposed ramp configuration.  I was not good at sketching, but my law degree came in handy in researching the building code, fire code, and RR regulations.  I refuted each of their objections.  

At several City Council meetings throughout 2003, more neighbors advocated for the open, gradual ramp design.  By December’s meeting, the City Council cried uncle.  The bad design was shelved, for lack of funding.  The emperor took his ball and went home.  

Two years later, I was sworn in as a member of the City Council, having included in my campaign platform a promise to fund livability projects like the bridge, the public park at Doyle and 61st streets (now called the Doyle/Hollis Park) and the bike lanes plus traffic calming measures on Adeline Street.  One year later, the Council voted to fund these projects.  I chaired the design committee that selected the engineering firm and the architect, sponsored community meetings, and eventually approved a detailed design that was finally constructed.  

Despite the design-by-committee aphorism, the bridge survived the design process.  My fellow committee members were a pleasure to work with -- they deserve credit:  Ken Bukowksi, Charles Debbas, Brian Donahue, Joseph Mudd (Novartis representative), Tim Doran (Novartis representative who replaced Joseph on the committee), John Scheuerman, Ann Weber, and Cedric Young (Bay Street mall representative).  The city staff member assigned to the committee, Ignacio Dayrit, was excellent.  Lastly, the chief engineer, Mahvash Harms, and the architect, Rick Phillips, were outstanding.  They produced a great bridge.

When I was elected to the City Council on a campaign platform of improving access for pedestrians, bicycles, and public transit riders, I proposed a number of other public works projects to make it easier for future parents with strollers to safely and comfortably walk to the Emeryville Marina from any Emeryville neighborhood.  These proposals included two bridge spans across I-80:  one at Temescal Creek, and another just south of Ashby Avenue.  The Temescal Creek bridge would complement the Bay Street bridge.  (Without a Temescal creek bridge across I-80, pedestrians heading west are still relegated to negotiating the Powell Street freeway interchange to get to the marina.)  For the proposed bridge near Ashby, an additional design committee was formed and held meetings.  When the City Council chose not to fund further design work (over my dissenting vote), the committee was disbanded.  

My daughters are now seniors in college.  I look forward to crossing the new span with them and their brother, Dean, and not having to hold our noses in an elevator.  Maybe someday, we will make it all the way to the Emeryville marina on foot without stepping into the Powell Street vehicle vortex.  


John Fricke is a longtime Emeryville resident, father of three, husband, lawyer, former Chairman of the South Bayfront Bike/Ped Bridge Committee as well as a former member of the Emeryville City Council.

Wednesday, November 24, 2021

South Bayfront Bike/Ped Bridge Grand Opening Celebration Slated for December 3rd.

Long Wait For Bike/Ped Bridge Finally Over

Completed Bridge Set to Open December 3rd



More than 25 years after it was first seriously proposed, Emeryville’s second bike/pedestrian bridge over the much cursed and city-bisecting Union Pacific railroad tracks, will finally be opened to the public December 3rd in a gala grand opening public ceremony planned for 6:00 PM.  

Former City Council member and Bridge Committee chair John Fricke, who as an outspoken critic of an early design of the bridge that didn't include bicycles, was outwardly sanguine but more likely sardonic about the December 3rd opening when he told the Tattler dryly, "Good things come to those who wait".


Not just a basic and prosaic over-crossing
Our new $21 million bridge is not without its charms,
even flirting with a sense of the dramatic.

The long awaited opening will finally silence a growing chorus from apprehensive residents about a boondoggle 'impossible bridge' and 'never bridge' and other such epithets.  

As with any large infrastructure project, this bridge, formally known as the South Bayfront Bike/Ped Bridge but called the Bay Street Mall Bridge by some, had its share of setbacks and colliding egos associated with its implementation.  Arguably more than its share.  

Madison Marquette, the Washington DC based developer of the Bay Street Mall, was an early promoter of a bridge at this location.  Seeing better connection for East Emeryville shoppers as a booster to its corporate bottom line, Madison Marquette pushed the City to build the bridge straight into their mall.  The City of Emeryville was listening and its Redevelopment Agency approved $8.4 million in 2003 to construct a pedestrian only bridge with elevators.   Mr Fricke cried foul to that concept, rallying instead for a multi-modal design with stairs for pedestrians and ramps for bikes (and wheelchairs).  Former City Council member Nora Davis and City Manager John Flores however fought against bikes on the bridge, insisting at first ramps not be provided.  Mr Flores, reiterating Ms Davis' concerns about unruly bicyclists, famously stated they represent a "ruffian element".   So Mr Fricke took his bike friendly design idea directly to the people.  The City responded with a ramp design that would have bicyclists dismount at switchback corners that would be too sharp and in conflict with wheelchairs, pedestrians and other bikers. 

The City, buckling to public pressure for a real bike/pedestrian bridge in response to a rising John Fricke who had subsequently been elected in a landslide victory to the City Council, finally appointed him as Chair of a newly commissioned South Bayfront Bike/Ped Bridge Committee in 2008.  Meanwhile, the cost had risen to $12 million and then $13.9 million owing mostly to delays associated with the redesign to accommodate bikes.  Councilwoman Davis and City Manager Flores finally gave up on their insistence on a pedestrian only bridge after they started receiving a lot of public support for Councilman Fricke's pro-bike design.  

The dissolution of the Redevelopment Agency, legal concerns with Union Pacific Railroad and City Council priority drift caused the bridge project to languish for years after Council member Fricke stepped down.   Finally in 2018, then mayor John Bauters, attempting to follow through on a campaign promise to voters, pushed the issue and convinced his colleagues to make the Fricke designed bridge a City priority issue.  By then the price tag had risen substantially and the Council finally signed a construction contract at $21.4 million (not including the eastern 'Horton Landing' approach from Horton Street).

The ballooning cost will likely soon be forgotten however when pedestrians and bikers begin using the long awaited infrastructure.  With this much needed bike/ped connection from East Emeryville to the Bay Street Mall, our town is on the cusp of being able to state with earnestness the oft repeated but heretofore glaringly unrealized proclamation of being a 'connected place'. 

The City will host a parade from City Hall to the bridge starting at 5:30 culminating in a ribbon cutting ceremony at 6:00 (ish) at the bridge followed by a party open to the public at the Bay Street Mall. 

Sunday, December 20, 2020

South Bayfront Ped/Bike Bridge Spans Railroad Tracks

Some 37 years after it was first proposed, a bridge for pedestrians (and bicycles) has finally spanned the railroad tracks between Powell and 40th streets in Emeryville.  At 11:15 Saturday night, a crane lifted the red steel pre-built arch over the tracks while workers busily fastened it down on both the east and west anchorages.  The next several months will bring completion of the ancillary approaches and other finishes.  Pedestrians and bicyclists will be able cross the completed span in summer of 2021.

The elevator at the pedestrian bridge
at the Amtrak Station was out of 
service again Saturday.
The new bridge, called the South Bayfront Ped/Bike Bridge will connect the Bay Street Mall with east Emeryville and get the City just a little bit closer to realizing its long standing General Plan shibboleth of Emeryville being ‘a connected place’.

As if by design to serve as a counterpoint, the elevator at the Amtrak Station pedestrian bridge that also spans the railroad tracks was out again on Saturday, a perennial frustration that has helped spur the new bridge. 

 The South Bayfront bridge has gone through a very tortured path over the years to finally get to this point.  Its first iteration, proposed by then City Manager Joe Tanner was a modest crossing only for pedestrians with stairs and elevators at either end.  Later, in 2005, a bicycle contingent led by soon-to-be-elected City Councilman John Fricke said any bridge built there must include bicycles.  Pushback against Mr Fricke’s bike friendly bridge idea came from the next City Manager, John Flores, who said bicyclists represented a “ruffian element” and that the bridge design should preclude bikes because bicyclists could use it as an escape route from crimes.  Luckily, Mr Flores’ argument didn’t win the day and after a selection process, the new design allowing for bike riders became the final plan.   As late as 2011, it appeared the bridge would never be completed after the State attempted to seize money set aside by the Emeryville Redevelopment Agency.  

After the City passed on an ambitious plan by the Emeryville based visionary architect/designer Eugene Tssui, the final design of the pedestrian/bike bridge has been called ‘pedestrian in use and design' in the sense that it lacks excitement or innovation.  It may not be too beautiful but it's certainly a long overdue stitching together of railroad divided east and west Emeryville.


A train roared past minutes before the crane began lifting the span into place.





It was all finished up by 12:30 AM.

Saturday, May 11, 2013

Sacramento OKs South Bayfront Bike/Ped Bridge

Councilwoman Jennifer West reports the South Bayfront Bike/Pedestrian Bridge, an Emeryville Redevelopment Agency project some ten years in the planning and subsequently killed when Sacramento dissolved redevelopment agencies statewide two years ago, has been revived.
The bridge is planned to cross the railroad tracks and connect the Bay Street Mall with Horton Street and points east.  The City of Emeryville won its case against the Department of Finance of the State of California on Thursday.  Ms West told the Tattler she will do everything in her power to move the project along as quickly as she can in the wake of this important victory.

Councilwoman West's blog post is HERE.

Friday, June 15, 2012

Letter To The Tattler: Ken Bukowski

Former city councilman and progenitor and spokesman for the Emeryville Property Owners Association, Ken Bukowski says we need to rethink the planned bike/pedestrian bridge over the railroad tracks at Bay Street called the South Bayfront Bridge.  The popular bridge was removed from consideration for funding by the State after the demise of the Redevelopment Agency, just as work was slated to begin.  Emeryville has already spent more than $2 million on consultants and engineers out of $13 million set aside by the Redevelopment Agency for construction of the bridge.  Mr Bukowski proposes going after Alameda County voter backed Measure B funds to complete the much needed bridge.
Here then is Mr Bukowski's letter:

.                 .                 .                  .


We Need The South Bayfront Bike/Ped Bridge
Let's Use Measure B Funds To Get It


As we move towards the November 2012 Election, is it possible for the City Council to support Measure B contingent on getting funds for the South Bayfront Bridge and potentially money for the Emery Go Round?
When the Alameda Transportation Authority came to the Council seeking support for Measure B, (extending the additional sales tax for transportation projects in Alameda County)  we still had the Redevelopment Agency.  But now, things are different.
Accordingly, the Council needs to re-examine its support for Measure B.


I will note: There is a huge imbalance of funds allocated for the South County which alone is reason to oppose the Measure.


The Measure includes funding for a Bart Extension to Livermore, (last time I checked BART extensions are about $250 million dollars per mile)  BART is the most expensive rapid rail system on Earth.
The anticipated ridership of the BART extension to Livermore does not justify spending the money.
BART is actually the reason why the Metropolitan Transportation Commission (MTC) exists.  A group of people in the Legislature in Sacramento gave the power to control all the transportation funding in the region to MTC instead of the Association of Bay Area Governments (ABAG) to provide on-going and endless funding for BART.


Since its existence, the MTC robs every other transportation provider to use money for BART.  They have tried to eliminate the transbay bus service many times, and the reason we are replacing the east span of the Bay Bridge (hard to believe but it's true), is to make sure there is never another transbay rail crossing like the old Key Route trains which will compete with BART.  The new east span is being constructed with only one third the carrying capacity of the existing bridge to make sure passengers trains can never run on the bridge again. 

The MTC spends almost $400,000 per year on lobbyists which in turn finds its way back to former legislators who created MTC.  The BART train system they created is non standard gage rail.  Every other train in the world has standard gage rail which means any train can run on any rail line, except BART.
As a consequence every BART rail car must be custom built at the highest price.   The manufactures of BART trains contributed heavily to former Senator Quentin Kopp, John Foran and others.  This region really got the shaft.
In every other region of the United States, the transportation funds are handled by the regional Council of Governments.


Emery Go Round
The BART extension to Livermore and numerous other south county projects are funded with Measure B money.   We should also seek funds for the Emery Go Round to ease the burden of funding for Emeryville property owners.  The success of the Emery Go Round translates into higher property owner assessments.
Many property owners are not happy about the success of the Emery Go Round.  Some of these property owners have limited income, vacant office and warehouse space.  They are not collecting increased rent money from tenants to cover the increasing cost of the Emery Go Round assessments. 
 Over the objection of some property owners, the Emeryville Transportation Management Association is spending resources to look at other alternative modes of transportation, which some feel is inappropriate.

The point of this memo is we should push to fund a portion of the Emery Go Round with Measure B money.  The huge price tag for the BART extension alone would justify both of these causes.
 Many of these south county projects have no value to us folks in northern part of the county. 


There is 8% funding in Measure B for ped-bike projects and the South Bayfront Bridge is one that should certainly qualify.  If this is measure is approved, the transportation authority would have broad power to allocate funds for other projects.
The bridge is a cost effective investment, since we have already spent considerable money on project design and readiness. 


We provide lots of sales tax revenue to the county and state and we are not getting our fair share in return.
When support for Measure B was first considered, we still had a Redevelopment Agency.  We should pursue every possible means to accomplish the South Bayfront ped-bike bridge.
I'm asking the Council to revise support for Measure B, contingent on receiving funds for the South Bayfront Ped-Bike Bridge, and potentially for the Emery Go Round.


Ken Bukowski

Friday, March 4, 2011

New Bike/Ped Bridge At Risk: $3 Million Already Spent

City Dilly Dallied, State Moves To Seize Funds:
South Bayfront Bike/Ped Bridge May Never Get Built

The people of Emeryville have been waiting for the South Bayfront bike/pedestrian bridge for more than a decade and now they may never see it at all.
City officials acknowledge the $13.5 million bridge, which is to cross the railroad tracks and connect the Bay Street mall to Horton Street near 53rd Street, is imperilled because of the Governor's plan to abolish redevelopment agencies state-wide.  City Hall it should be noted, is not so keen to acknowledge the bridge has been put in danger because of its own slow pace building it.

An early iteration of the bridge design:
$3.5 million may be lost forever
The State will consider next week, the fate of redevelopment agencies and should it be decided to abolish them, the South Bayfront bridge might not be possible to be built according to Helen Bean, the city's Economic Director.  She noted there could be a lawsuit to stop the Governor's plan from the California Redevelopment Association, a non profit legislative advocacy group forwarding the interests of redevelopment agencies.  At that point, according to Ms Bean, it would be "unclear what Emeryville's Redevelopment Agency could do" in terms of building the bridge.

Building the bridge has been a city priority for some 15 years but has been recently picking up speed.  The design aspect has been completed to the tune of $3.5 million and that money is not recoverable if the State stops Redevelopment Agency obligations for the remaining $10 construction contract.  In the best case scenario, the contract for construction could go out in June according to Ms Bean.

For the first seven years or so, the city moved slowly on building the bridge, fighting bike advocates as former City Manager John Flores together with the council majority pushed to keep bikes off the bridge preferring a pedestrian only span.  An engineering firm consequently was hired to design a pedestrian only bridge.  Former council member John Fricke built his campaign for election on building the bridge and making sure bikes would be able to use it as well.  Mr Fricke succeeded and the South Bayfront Bike/Pedestrian Bridge Committee was ultimately formed.  If the construction contract for the bridge is allowed, city officials say it should take 18 months to two years to complete the work.

The city's new general plan and the bike/ped advisory committee has explicitly stated the bridge is necessary for a livable town.  Ms Bean agreed and she weighed in on the consequences of a State revocation of redevelopment agencies, "If the [Emeryville] Redevelopment Agency is not able to build the bridge because of the Governor's proposal to dissolve redevelopment agencies, that would be a tragic loss for the city".

With Sacramento bearing down, the city is now facing the possibility that the whole endeavour will be for naught, considering that precious time was lost early in the fight over who would get to use the bridge.

Saturday, February 26, 2011

New Bike/Ped Bridge On Ohlone Indian Burial Site

Ohlone Indian Bones Found At Emeryville Bridge Site


Depiction of what's now Emeryville
before the arrival of the Spanish in
the late eighteenth century.
The Emeryville Redevelopment Agency will vote on a resolution March 1 to retain an archaeological service company after test borings for the proposed bike/pedestrian bridge connecting Bay Street and Horton Street encountered human skeletons last month.  An initial report to the city council claims the human remains are "thousands of years old" and are of native American origin.
The Alameda County Coroner was contacted and after confirming the bones were human, the bridge contractor notified the Native American Heritage Commission according to the report.  The remains were carted off the site for safe keeping and a team of "most likely decedents" will help re-inter the remains upon completion of the bridge.  The Coroner says the remains are from two individual humans.

The eastern landing of the proposed bridge is where the remains were found and a future small park there called Horton Street Landing will be the final resting place for the two individuals.  The council report says the decedents team will decide the actual final burial site within the park and it will not be publicly disclosed.

Early Emeryville residents.
A February 11 letter to the City Engineer from the archeology firm states the added work is not covered in the nearly $14 million bridge project known as the South Bayfront Bike/Pedestrian Bridge and is asking for an additional $41,567 for the excavation and re-burial work.