New Traffic Count Report: Emeryville's Entire Bike Boulevard Network Unsafe


Mounting Traffic Puts Bicyclists in Danger

All Five Bike Boulevards Now in Violation 

A recently released report by the City of Emeryville shows an alarming rise in vehicle traffic that now exposes bicyclists to danger on every bike boulevard in town due to unsafe volumes of traffic.  The internal report, entitled Vehicle/Bicycle/Pedestrian Counts (Fall 2019), was generated as a result of a Bike Plan required bi-annual traffic count and shows a rapidly deteriorating environment for bicyclists in Emeryville as compared with the last traffic count conducted by the City.  All five bike boulevards in Emeryville are now unsafe for bicycling according to the City’s own metrics and one, the 45th Street Bike Boulevard, is saddled with vehicle traffic 96% in excess over the safe limit.

The City has been aware the increase of vehicles using the town’s bike boulevard network is putting bicyclists in harm's way for some time but up until this latest traffic count report, at least one bike boulevard has always been shown to be within safe parameters.  Now that the Doyle Street Bike Boulevard has gone over the limit, that can no longer be claimed.

From the New Traffic Count Report
Emeryville's High Average Daily Traffic Allowances: Not High Enough.
Palo Alto's bike boulevard network allows for a maximum of 750 ADT.

The bike boulevard network was created in 2009 as a response to Emeryville’s anticipated growth the new General Plan provided for.  It was determined at the time, some streets should be set aside as bike priority streets to allow for bicycling to remain a viable alternative to driving.  Emeryville spent $200,000 on consultants who recommended the City create a network of these streets, bike boulevards, based on how other cities have done it.  The business and developer community however, not wishing their driving clients/tenants be constrained, cried foul.  As the Bike Plan was being finalized, the City Council unilaterally increased the allowable traffic on the network (over any other city in the Bay Area) to mollify the business community's concerns, especially on the highly contested Horton Street where the allowable traffic loads were doubled.  Traffic however has risen apace since then and now, even that increased allowance for traffic on our bike boulevards is not enough.

Against this backdrop, the City Council has been unwilling to implement the traffic calming remedies spelled out in the Bike Plan to reduce the rising vehicle traffic to the safe-for-bicyclists minimum called out by the Plan.  Developers and businesses near the bike boulevards have repeatedly told the Council that the specified traffic calming remedies are unacceptable and these have been the voices the Council has listened to up until now.  The predictable unsafe traffic volumes now seen on the bike boulevard network is due to the Council’s inaction in this regard.

It’s Going To Get Worse
Already Approved: the BMR Project
2400 parking spaces netting 4800 driving
trips per day will be added to an already
overburdened Horton Street.
The recent leap in traffic is a portent for what is to come.  The General Plan targets Emeryville with a population of 16,600 residents by 2029, the Plan’s sunset.  Added to the increased driving population will be a dramatically increased business footprint.  These eventualities will likely add lots of traffic to our existing grid regardless of Council hopes for a wholesale turn in public sentiments towards public transit.   Additionally the City Council, entertaining overturning existing housing unit mix regulations to accommodate residential super towers such as the Onni project slated for Christie Avenue, has hinted the 16,600 mark is a number they intend to race past rather than target.

One looming non-residential project, the BMR life science 'Center of Innovation' slated for Horton and Hollis Streets, will include 2400 new parking spaces delivering a new glut of 4800 Average Daily Traffic (ADT) trips to Horton Street.  Adding to that number, the approved Sherwin Williams project with at least an extra 4000 ADT and an unspecified amount of traffic from the newly completed but not yet fully rented Transit Center, Horton Street, already 38% over the limit, will not be a street for conducive for biking regardless of the plethora of purple signage proclaiming its bike boulevard status.

The City Council effectively took Horton Street out of contention as a possible street for bike transit when they issued a 'Statement of Overriding Considerations' in the run up to the approval for the Sherwin Williams project in 2016.  The SOC stated that the project will overturn the Horton Street Bike Boulevard but the community benefits of the project outweigh bike concerns.
More recently, the Council decided to not implement the Bike Plan  traffic calming treatments for the 45th & 53rd street bike boulevards, choosing instead to let the clock run out for the two streets.  The remaining boulevards on the network, Doyle Street and 59th Street don't seem likely candidates for traffic calming given the City Council's lack of concern for the Bike Plan combined with an aggressive view towards growth the Council has exhibited over and beyond what the General Plan provides for and traffic, accordingly, will likely overrun these two streets as well.

Sunday, April 8, 2018

History of Bad Bike Policy Nets the City of Emeryville a Countdown Clock




Introducing:
The 53rd and 45th Street Bike Boulevards 
Countdown Clock

City Council: Be Warned


The policy makers at Emeryville City Hall have a way of forgetting about programs they don’t much care for and insofar as these programs are mandated by the General Plan and have a prescribed implementation timeline therein, the Tattler has always been there to gently remind them.  However, even our rigorous oversight has not been enough to coerce the decision makers to implement the Bike Plan, the part of the General Plan that City Hall historically has had the biggest aversion to.  
Owing to this intolerable situation, the Tattler now introduces the 53rd and 45th Street Bike Boulevards Countdown Clock.  The clock will be located at the bottom of the front page of the Tattler (phone users will have to load the web version to see it).  It will remain until the City places the traffic calming measures on these two streets the Bike Plan mandates.  Alternatively, the City Council could amend the Bike Plan to remove the traffic calming requirements for these two streets and then the Clock would be taken down.

Every Two Years
The 53rd and 45th Street Bike Boulevards Countdown Clock is set to run out to zero on September 14th, 2019 at 5:00 pm, the latest possible time the City has to implement the next required level of traffic calming measures placed on the two streets.  The clock began on September 14th, 2017 after the required official traffic count was completed when the City became aware that there is too much vehicle traffic on the two streets.  The City conducts the traffic counts on every Bike Boulevard every two years as the Plan stipulates and if an “overage” of traffic is found, the City is required to emplace traffic calming measures, after which a new countdown begins.


It is hoped the City Council will look to the Tattler 53rd and 45th Street Bike Boulevard Countdown Clock in place of their staff who has been negligent in reminding them of their duties regarding the Bike Plan.  Since the staff has opined that temporary traffic calming measures need to be emplaced for at least six months before a new traffic count can be considered reliable, the Council is reminded the clock only records the actual time when the measures need to be on the roadways and it doesn’t take into account any internal scheduling policies.  
The City needs to do its due diligence and make sure the clock doesn’t run out without the next traffic calming measures in place on 53rd and 45th Streets.  Additionally, the Clock will not be reset except insofar as duly prescribed Bike Plan traffic calming measures are implemented.  And warning to the elected officials: the Clock will help serve as the people’s accounting device at election time.

Thursday, March 1, 2018

Bike Plan Reinterpreted: 45th & 53rd Street Bike Blvds Languish


Bike Plan Unilaterally Reinterpreted

City Hall’s New Vision Means Traffic Calming Must Wait for Bike Boulevards

1,143 Cars Per Day Over the Allowable Limit

City Council Refuses to Protect Bicyclists

Level Four Goalposts Moved 


The City of Emeryville Public Works Department has announced it is unilaterally reinterpreting its Pedestrian/Bicycle Plan, adding additional procedures and making it more difficult to protect designated bike boulevards from excess vehicle traffic.  Elucidated in a recent letter to the Tattler, the City Hall staff generated reinterpretation changes the traffic calming ‘level’ system in the Bike Plan, adding many more steps to each level before a designated bike boulevard can move forward to the next level of traffic calming.
The new policy, revealed by the Public Works Department, states that “multiple iterations”, of a particular traffic calming level should now be conducted before the Council would be advised to consider raising the street to the more rigorous next level, theoretically adding decades before a bike boulevard would reach the highest level of protection (Level Five).

At stake is bicycle safety on our Bike Boulevards as the new interpretation hamstrings the City in effectively dealing with an unsafe amount of vehicle traffic sharing the road with bicyclists that the Bike Plan was formulated to protect against.  By adding new steps for each level of traffic calming, the staff presumes to speak for the Bicycle/Pedestrian Advisory Committee (BPAC) and the City Council that certified the Plan (without the stringent new metrics) in 2009.  It is informative that before the new staff interpretation, bike boulevards were moved up in level without these extra steps for each level. 
Indeed, several streets in our town have moved up from Level One to Level Three traffic calming over the years, where they now appear to be stuck, as is the case with the 45th Street and 53rd Street Boulevards. The new tougher policy now effecting these two streets will require more iterations of Level Three traffic calming elements be installed before they can move up to Level Four. 
If the City Council really wanted to implement
the Bike Plan, they could do it.  It's the

'stick to it' step they can't seem to accomplish.
It's either Attention Deficit Disorder (ADD) or 
Developer Surplus Disorder (DSD) indicated.
Symtoms are the same.
Remedies would be Ritalin or 
Electorate Reckoning respectively.

A recently conducted traffic count reveals those two streets are shown to have 1,143 (45th St) and 638 (53rd St) too many cars in Average Daily Trips (ADT) to be considered bike boulevards by the Plan.  But regardless of the excess traffic on these specific streets, the staff has ruled neither street is ready for a level ‘upgrade’ because of the new metric of “[up to] five elements” of Level Three traffic calming measures have not yet been installed.  
For a complete description of each traffic calming level, please see the chart below. 

The 45th and 53rd Boulevards join the former Horton Street Bike Boulevard in languishing; all three hitting a wall at Level Three traffic calming regardless of their excess vehicle traffic.  Notably, the previous head of the Public Works Department Maurice Kaufman and the previous City Council member Nora Davis both declared Level Four calming for any Emeryville street a ‘no go zone’; being too onerous for vehicles as described by developers wishing to build auto-centric projects near the Boulevards.  Accordingly, an earlier traffic count conducted by the developers of the Sherwin Williams project that also showed too much existing traffic on all three streets, was ignored by Ms Davis and the rest of the City Council.  Later, Mayor Dianne Martinez steadfastly and unilaterally refused to move the two streets, 45th & 53rd, to Level Four as the Tattler reported in 2016.
On Horton Street,  the City Council refused to institute Level Four traffic calming elements and instead issued a ‘Statement of Overriding Considerations’, stating the Sherwin Williams project is more important than the Horton Street Bike Boulevard and that the City would ignore the Bike Plan remedy for excess vehicle traffic.  The Statement of Overriding Considerations signaled to the community that the City Council has no intention of supporting bike boulevard status for Horton Street.  Regardless, before they were elected, both Dianne Martinez and Scott Donahue promised Level Four traffic calming for Horton Street.

The 45th and 53rd Street Bike Boulevards have not been subjected to a statement of overriding considerations but the City Council is continuing to let them languish, unrealized as bike boulevards.

The Bike Plan calls for traffic counts to be conducted every two years, a fact the Public Works Department now acknowledges even though the Department was caught lying to the City Manager about that in 2014.  The Tattler uncovered an internal document by use of a Public Records Request that showed how the Department was going to extraordinary lengths to prevent a street moving to traffic calming Level Four by attempting to get the newly hired City Manager Carolyn Lehr to ignore the Bike Plan.  In the memo, the Public Works staff told the new City Manager the Bike Plan says traffic counts are not to be conducted every two years, but rather only if a substantial construction project happens on the street in question or if a large number of citizen complaints are registered; an outright falsehood.  The Bike Plan is very clear that traffic counts must be conducted every two years without conditions.


The new interpretation of up to five required applications of Level Three elements (up from one) being ‘required’ may be the latest attempt by the City to stall implementation of Emeryville’s Bike Plan.  The City has felt no compunction against moving any Bike Boulevard speedily forward through Levels One to Three but they haven't thus far been able to make the breakthrough to Level Four, forwarding different reasons that change over time as to why it can't be done.  The latest prohibition against Level Four in the form of the unilateral Public Works reinterpretation seems to be just the latest blockage offered up by an ignominious City Hall.  It would seem the admonitions against Level Four traffic calming by the assailing Maurice Kaufman and Nora Davis made years ago are still the modus operating principles at City Hall.  

Bike boulevards are supposed to be "cars allowed but bikes preferred" streets meant to maintain bicycling as a safe and convenient form of transportation by discouraging motor vehicle use.  Developers and the business community have long tried to dissuade the City Council from enacting effective traffic calming on Emeryville's Bike Boulevards.


From the Emeryville Pedestrian/Bicycle Plan
Level Four=street narrowings, Level Five= full and partial closures
Level Four (and Level Five) have been determined to be too effective 
so the City has resisted implementing them on any street.  The City Council however has not 
seen fit to amend the Plan to remove these two highest levels they don't like, probably because 
they don't want to be perceived by the public as anti-bike.







From the Bike Plan
53rd Street is at the top of the photo, 45th on the bottom with Horton Street to the left.

North is up, east right, south down and west is left.
The Average Daily Trip (ADT) is supposed to be no more than 1500 for the eastern sections of
45th and 53rd Streets.

53rd Street From the Latest Traffic Count
The eastern section of 53rd Street has 2138 Average Daily Trips or
638 over the maximum allowable amount.  Since the street is now at Level Three, 
that should mean 53rd Street is a candidate for Level Four traffic calming elements.
The Public Works Department says NO however.




45th Street From the Latest Traffic Count
The eastern section of 45th Street has 2,643 Average Daily Trips
or 1,143 over the maximum allowable amount.  A City Council
that cared about bicycling would impliment
Level Four traffic calming elements for the street.
A traffic count from years ago east of San Pablo Avenue
showed 45th Street with more than 3000 cars per day.
Note the vehicle speeds are too high also.



Earns Two Smiling Nora Davis's
Nora Davis smiles down on
the Public Works Department 
and the City Council!

Saturday, December 31, 2016

Another Year Passes, Still No Horton Street Bike Boulevard


It's déjà vu all over again
December 31, 2016 is like December 31, 2015;
Bike Plan Still Being Ignored

Today, the Tattler brings back our ongoing end of December yearly feature: We re-post our original September 2012 story (below in non-italicized print) on Emeryville's Horton Street Bike Boulevard every December 31st and will continue every year until City Hall either stops stalling and implements our Bike Plan or if they refuse, amend our Bike Plan and remove Horton's Bike Boulevard status, additionally they could amend the Plan to allow more than 3000 vehicle trips per day on Bike Boulevards.  Those are their only choices available as dictated by the Plan.  Stalling is not allowed.  This end-of-the-year feature serves as an annual clearinghouse for any news on the hold up of the Horton Street Bike Boulevard over the previous year.   
Readers bored or exasperated with the ongoing story of City Hall inaction on Horton Street can simply read the year end synopsis in the italics preceding the September 2012 re-post every December 31st here: 

2016 Synopsis-
"I wake up every day, right here in 
Punxsutawney, and it's always 
February 2nd [or December 31st 
in Emeryville], and there's nothing 
I can do about it."

In 2016, the Horton Street Bike Boulevard finally died with the signing of the Sherwin Williams Statement of Overriding Considerations. Before that fateful day, the City Council voted to place Level Three traffic calming measures in the form of three temporary speed bumps along Horton Street between 45th Street and 53rd Street.  The bumps went in in November.  It represented no forward movement for the implementation of the Horton Street Bike Boulevard because Horton Street was already at Level Three and because the street still remains substantially more than 3000 vehicle trips per day (the cut off point where a street can be called a bike boulevard).  The speed bumps have been called out as unlikely to succeed in bringing down the volume of traffic by Alta Planning, the writers of Emeryville's $200,000 Bike Plan but may cause vehicle speed to be reduced.  Additionally, the Level Three speed bumps are counter to what Mayor Scott Donahue and Councilwoman Dianne Martinez promised voters in 2014 when they said they would move Horton Street to Level Four traffic calming (chicanes or chokers).  Notably, City Engineer Maurice Kaufman said he would not allow any Level Four or Level Five traffic diversion in Emeryville regardless of the Bike Plan's requirements for it.  But the most important event of 2016 is the Sherwin Williams decision and it's Statement of Overriding Considerations signed by the City Council that says Horton Street will have 4000 vehicle trips per day forever (with more coming every year) rendering a bike boulevard impossible for Horton Street.  This year end wrap up at the Tattler will continue until the City Council finally amends our Bike Plan and removes the bike boulevard status for Horton Street returning it to a regular street.

1998-2015
In 1998, Emeryville adapted its Bike Plan after years of study and $200,000  subsequently spent on it.  In 2013, the City Council agreed to spend $10,000 to study the Bike Plan to figure out how to implement the Horton Street Bike Boulevard required by the Plan.  This $10,000 study is referred to as the 'study of the study'.  The Bike Plan doesn't call for any studies to be done to implement its requirements, it should be noted.  In 2014 City Hall held two community meetings about the study of the study but no action on Horton Street was taken that year or the next year (finally came in the form of the November 2016 speed bumps).  Also in 2014, City Hall found out another Bike Boulevard, the 45th Street Bike Boulevard is also in violation due to too many cars on that street.  Nothing has been done to rectify that either.  The Tattler investigation of the 45th Street and Horton Street problems was revealed when we reported the City Engineer lied to the City Manager to stop the Horton Street Bike Boulevard.  

Here then is the September 29th, 2012 Tattler story we re-print every December 31st:


Major Traffic Calming Long Past Due For Horton Street

Emeryville's premiere bicycle thoroughfare, the Horton Street Bike Boulevard, has so much high speed traffic that it has become unsafe for bicycling.  So says Alta Planning, a Berkeley based urban bike network design firm that was commissioned by the City of Emeryville to study bicycling in town.  The $200,000 study, now incorporated into Emeryville's Bicycle/Pedestrian Plan and adopted into law by the city council lays waiting, ready to be implemented.
The question is, will it really be implemented or will it languish in some dusty corner at City Hall as so many other expensive studies have done?  Given the city council's baleful history of failing to calm the traffic on Horton Street for bicycle traffic and working to improve the street for vehicle use at the expense of bicycling, it seems likely it will be ignored and will remain a major automobile thoroughfare, unsafe for bicycles and becoming increasingly more so over time.  

Central to the Alta study is a limit on the number of cars that may use Horton Street, set at 3000 vehicles per day, before a mandatory set of traffic calming procedures kicks in.  The idea is that the traffic calming fixes will lower the number of vehicles that use the bike boulevard down below the 3000 maximum.  It should be noted Emeryville's 3000 number earmarked for bike boulevards is larger than any other city in the Bay Area. 

A choker is an example of a 'neck-down'
called for by level 4 traffic calming.
The prescribed traffic calming comes in a series of increasingly interventionist levels, one through five, that reduces traffic volume and speed, the last such level resulting in a total diversion for through traffic.  Each level requires two years to adequately assess its efficacy.  

At this point, Horton Street has already gone through the first three traffic calming levels; these involve street stenciling, signage and intersection "bulb-outs".  Now, since traffic has not subsided on Horton (it's actually increased), it's time for level 4 traffic calming to be implemented according to the Plan.
Level 4 calls for "significant traffic calming", specifically, 'neck downs' or traffic limiters such as 'chokers', designed to act like a one lane bridge permitting only one car through at a time.

Here's what the Bike Plan calls for on Emeryville's bike boulevards:

Level 1 Basic Bicycle Boulevard- signs, pavement markings
Level 2 Enhanced Bicycle Boulevard- way-finding signs, reduced delays at intersections
Level 3 Limited Traffic Calming- intersection bulb-outs
Level 4 Significant Traffic Calming- neck-downs
Level 5 Traffic Diversion


Level 5 calls for diverters: This
is called out only if level 4 doesn't
work after two years.
The problem is the Bike Committee has already twice voted on significant traffic calming for Horton Street in years past.  Both times the city council has overridden the committee's findings.  The last time the committee voted unanimously to add such calming, councilwoman Nora Davis explained her veto to the committee, "I have no problem putting paint on the asphalt [pavement markings]" but anything more dramatic than that would draw a veto from her and consequently also from the council majority.

In the intervening two and a half years since the last council veto shutting down Horton Street traffic calming, the city has commissioned and now encoded the $200,000 Alta study.

While we acknowledge Ms Davis' forthrightness in explaining to the people why they shouldn't expect safe biking routes in town, we call on the rest of the council to abide by the new Bike Plan they have adopted.  The fact that other such documents have been subverted in the past by the council should not serve as a precedent for inaction on Horton Street.  It's never too late to start working towards livability and rational public policy.  Let's make bicycling safe on the Horton Street Bicycle Boulevard.  It's time for a choker on Horton Street.



Thursday, July 7, 2016

45th & 53rd Streets: Mayor Says Emeryville's Bike Plan Will Not Be Implemented

Mayor: Settled Bike Plan Not Needed,
Will Be Superseded

45th & 53rd Streets Won't Get Bike Plan Treatment 

Emeryville’s Mayor Dianne Martinez announced recently she intends that City Hall’s certified Bicycle Plan be superseded and a new set of extralegal metrics, identified by her and not voted upon by the City Council, take the place of the Plan’s previously adjudicated traffic calming measures for our bike boulevards.  Ms Martinez said in an email that two previously scheduled street improvements not recognized by the Bike Plan will satisfy the requirements to limit the number of vehicles using both streets and that the Bike Plan is unneeded.  The sentiments relayed by the Mayor represent the first publicly professed retrenchment or abandonment of Emeryville’s five year old Bike Plan expressed by a City Council member even though in previous deeds the Council has shown a propensity to disregard the Bike Plan.
Emeryville Mayor Dianne Martinez
We need not be locked in by our
General Plan or our Bike Plan,
we can make stuff up as we go along.


The City of Emeryville has identified 45th Street and 53rd Street as Bike Boulevards and thus subject to a General Plan/Bike Plan mandated program of directing vehicles to other streets known as traffic calming, to assure bicycle safety for these bike priority corridors.  However 45th & 53rd streets have languished since 2012 when the Bike Plan was certified by the Council, the two streets saddled with too many cars to be considered bike boulevards by City Hall and no interest up until now has been shown to rectify the unsafe condition there. 

Regardless of a 2015 traffic study revealing the extent of the unsafe vehicle traffic, an amount of traffic in excess of what’s allowed by the Bike Plan, the City has remained unmoved, doubling down instead on their insistence to continue to ignore the problem.  This has come in the form of a recent email from Mayor Dianne Martinez to the Tattler explaining that the City’s Bike Plan need not be enforced at all for these two streets.
The Mayor says traffic calming is coming to the two streets independently of the Bike Plan; a traffic circle for 53rd Street and a new crosswalk for 45th Street even though these are not identified by the Bike Plan as legitimate traffic calming measures.  Ms Martinez refused to qualify the two unrecognized traffic calming solutions in her email, suggesting she believes traffic calming methods are all the same as far as reducing traffic is concerned.  She answered the Tattler in the email, “In short, the City has indeed initiated traffic calming for these two streets. The City has started working with Pixar to implement a mid-block crosswalk/traffic-calming measure on 45th. On 53rd, the Emeryville Center of Community Life is constructing a traffic circle, which is a calming measure”.

The Bike Plan's regime of traffic calming measures was commissioned by Emeryville in a study by Alta Planning of Berkeley at a cost of $200,000.

The Bike Plan, formulated over two years by Emeryville’s Bike Committee with public input and with help from Alta, provides vehicle traffic metrics for bike boulevards, taking pains to note too many cars on a bike boulevard is unsafe.  The Plan gives a detailed prescription for what to do if too many cars are using the boulevard; a specific suite of traffic calming measures with increasing intensity (Levels 1-5) is the remedy for an excess amount of traffic. 
Mayor Martinez is disregarding the democratically (and professionally) agreed upon process laid out by our Bike Plan stating other measures, not included in the Plan that happen to be forthcoming on the two streets that she herself has identified as traffic calming, are all that is needed. 

Vice Mayor Scott Donahue, who ran as a slate mate with Ms Martinez and as an advocate for bicycles specifically, refused to comment regarding the Mayor’s would be new City policy for 45th & 53rd Streets.

The traffic counts revealing the excess traffic for bike boulvards in the area, including the Horton Street Bike Boulevard, were conducted in 2015 as a condition of the draft environmental documents for the Sherwin Williams development project.  The Bike Plan requires the City to conduct its own traffic counts to monitor its bike boulevards but none have been conducted so far.  The Tattler revealed in 2015 through a Public Records Request of internal documents at City Hall that the Public Works Director Maurice Kaufman was attempting to hide the traffic study requirements from the newly hired City Manager Carolyn Lehr.  This year the City finally has funded money to conduct the required traffic counts beginning in 2018, presumably as a result of the Tattler investigation.

Sunday, May 1, 2016

The City of Emeryville is Anti-Bike

The City Staff Thinks Bikes Are OK*
*as long as they don't inconvenience vehicles

 Mayor, Vice Mayor 
Have a Staff Infection

Emeryville Mayor Martinez
Agrees with the staff:
Now is not the time
to implement the Bike Plan.
She's been infected.
Opinion
The people of Emeryville want a bike boulevard on Horton Street.  How do we know that?  Well, for one, because it's specified in our city's General Plan and our GP is the most democratically vetted GP of any in the Bay Area.  Our GP even won an award for the record high levels of support from the residents.  Further and more compellingly we know the people of Emeryville want a bike boulevard on Horton Street because that's what they directly voted for in November of 2014 when they cast their votes for Dianne Martinez and Scott Donahue both of whom were definitive at the time: a vote for them is a vote for the Horton Street Bike Boulevard they assured us.
The people like the idea of the Horton Street Bike Boulevard but the staff at City Hall sure doesn't.  In fact they've worked for years trying to make sure the traffic calming provisions spelled out in our Bike Plan don't come to pass on Horton (or any other street in Emeryville designated as a bike boulevard).

Vice Mayor Donahue
Agrees with the Mayor.
He's also infected.
The citizens voted for Dianne and Scott, finally getting a City Council majority that appeared to support the resident's desires for a bike boulevard on Horton Street....that's good.  But we were saddened when the two voted down the Bike Plan provision for traffic calming at the now infamous April 5th City Council meeting vote covered by the Tattler.  What's up with that?  They were very clear before the election they would vote for Level Four traffic calming as the Bike Plan delineates and then they reversed themselves and supported the staff who says NO to Level Four calming claimed to be something too restrictive against car traffic.

Staff Infection
The Mayor Dianne Martinez and the Vice Mayor Scott Donahue have been infected by virulent anti-bike sentiment festering at City Hall; they have a staff infection.  After listening to the residents before the election, now they're listening to the staff.  Whereas before they thought there should be a process and we should follow the General Plan's remedy for too much car traffic on bike boulevards, now they think like how the staff thinks; the General Plan is too radical, especially as it pertains to bike boulevards.  Dianne and Scott have joined a long procession of City Council colleagues who have been similarly infected: OK applying stencils to the streets or putting up purple bike boulevard signs but once drivers begin to become inconvenienced, well that's "too extreme" as the City Manager likes to put it.

The lengths the staff is willing to go to stop the Bike Plan's traffic calming is pretty exceptional.
To wit:
The Staff
Their effect is corrosive and infectious on the
body politic if the Council doesn't inoculate
themselves with the disinfectant of 

independence and allegiance to the people.
What's also exceptional is the fact that our two newest Council members are so unexceptional; so far no Council members have shown a willingness to go against the staff on bike boulevards.  But what sets the Mayor and Vice Mayor apart is the iron clad promise they made to voters they would implement Level Four traffic calming on Horton Street if elected.  Other Council members have made vague references over the years to their support of the Bike Plan and about how much they like bicycling and other innocuous stuff.  Dianne and Scott bumped it up a notch with a specific promise.

We're still not sure why this overt bait and switch has happened (other than another outbreak of staff infection).  Vice Mayor Donahue has so far refused to comment.  Mayor Martinez has told the Tattler that while she agrees the staff has a jones against bike boulevard traffic calming that she doesn't share, she's too weak to stop them (presumably) and that Level Three traffic calming is the best we can do, "a bird in the hand..." and so on she said.

After a year and a half with these two progressives on our City Council, we've been worried that the same old pattern would repeat itself.  The fact that there's been no shake up at City Hall has proved to be a harbinger of the status quo being unperturbed by the new condition of a progressive Council majority.  One would expect a radical new direction selected by the voters to be reflected in a new culture at City Hall but these two decided to keep the same crew on.  The same department heads selected by the long ensconced pro-developer Nora Davis council majority have been left be in their corner offices, their power undiminished.  The resultant push back against Level Four traffic calming for Horton Street is what one would expect in such a scenario.

At least two more bike boulevards, 45th Street and 53rd Street, are now over their traffic thresholds and are over due for traffic calming as mandated by the Bike Plan.  After the progressives on the council joined their conservative colleagues in opposing the implementation of Horton Street traffic calming, we expect they'll do likewise for the other bike boulevards.  Barring some major change, we can't see the Bike Plan mandated traffic calming (over level three) being implemented for any street.

Emeryville; the more things change the more they stay the same.  Where's our Jonas Salk?  We're pretty discouraged here.

Saturday, January 23, 2016

Sherwin Williams Project: 'Cars Are Good, Bikes Are Incompatable'

Sherwin Williams Primer:
'Bike Boulevards Not Acceptable'

EIR Says Glut of Cars Should Push Bikes Out
If All Goes to Plan 

There's only one way the 540 unit Sherwin Williams project gets built; and that's by accommodating its glut of cars seeking its 1000 parking spaces by getting rid of Emeryville's General Plan mandated Bike Boulevards on Horton Street (as well as 45th and 53rd streets) according to City Hall and the environmental document it directed for the project.
But it wasn't supposed to be this way. The document prepared to study the effects of the Sherwin Williams residential building development proposal that has been written that precludes the three planned bicycle boulevards was specifically supposed to accommodate the bike transit corridors in its traffic analysis.  Emeryville's Directors of Planning and Public Works made an executive decision as it turns out, to only study one traffic scenario for the project; one that disregards the three bike boulevards.  The document was supposed to assist the City Council in their decision about the Sherwin Williams proposal as if bike boulevards could coexist with the cars.

"It didn't occur to us" 
to accommodate bike boulevards
-Charlie Bryant 
Emeryville Planning Director

The State mandated document, called the Draft Environmental Impact Report (DIER), was prepared by Maurice Kaufman, City Hall's Public Works Department Director as well as Planning Department Director Charlie Bryant by deleting from the City's General Plan the bike boulevards and moving the project forward with a field leveling, full steam ahead Statement of Overriding Consideration for the City Council to sign.  Alternatively, the bike boulevard standards quantified by the Emeryville's Bike Plan (part of the General Plan), could be "loosened" by amending the Bike Plan to permit the piling of more cars onto the bike corridors Mr Kaufman told the Tattler Wednesday.  However Emeryville's allowance of 3000 vehicles on its bike boulevards is already very high by national standards, "That's probably too high" Steve Clark, the 'bike friendly community director' at the League of American Bicyclists told the Tattler last summer.  Regardless, four years ago, Emeryville's Bike Plan was recognized by the League as good enough to award the city with the designation 'bicycle friendly city'.

Emeryville's General Plan provides for no more than 3000 vehicle trips per day on the three bike boulevards and provides a remedy of traffic diverters to maintain that metric.  Mr Kaufman and Mr Bryant directed the DEIR to assume two 'half diverters' for Horton Street, one at 40th Street and one at 53rd Street that would permit southbound traffic only and northbound traffic only respectively, in order to try to bring down the number of vehicles on the street but the study reveals the remaining traffic would still exceed the 3000 vehicles per day limit as the Bike Plan spells out.  The scenario studied in the DEIR calls for no diverters for either 45th Street Bike Boulevard or the 53rd Street Bike Boulevard.
Directors Bryant (L) and Kaufman (R)
Bike boulevards are only possible
"If you loosen your standards" (Kaufman)

 because "It didn't occur to us" (Bryant)
 to accommodate bikes (as mandated 
by the General Plan).
The DEIR could have studied the traffic effects of the Sherwin Williams project with enough diverters on the bike boulevards to accommodate Emeryville's Bike Plan but Planning Director Bryant told the Tattler that idea wasn't entertained, "That didn't occur to us" he said.  For its part, LSA Associates, the firm that actually wrote the DEIR thinks the two half diverters as proposed by City Hall, while not adequate to save the bike boulevards, are the "maximum that is feasible", a representative told the Tattler.

The public is allowed to comment on the DEIR and any comments received will be reflected in the Final Environmental Impact Report (FEIR) as well as any responses deemed reasonable from LSA Associates.  Commenters should contact the City of Emeryville.

Thursday, December 31, 2015

Yet Another Year Passes, Still No Horton Street Bike Boulevard


It's déjà vu all over again
December 31, 2015 is like December 31, 2014;
Bike Plan Still Being Ignored

Today, the Tattler brings back our ongoing end of December yearly feature: We re-post our September 2012 story (below) on Emeryville's Horton Street Bike Boulevard every December 31st and will continue until City Hall stops stalling and implements our Bike Plan as they are required to do.  This end-of-the-year feature serves as an annual clearinghouse for any news on the hold up of the Horton Street Bike Boulevard over the previous year.   
Readers bored or exasperated with the ongoing story of City Hall inaction on Horton Street can simply read the year end (short) synopsis in the italics preceding the September 2012 re-post every December 31st:  
I wake up every day, right here in 
Punxsutawney, and it's always 
February 2nd (or December 31st 
in Emeryville), and there's nothing 
I can do about it.

2015 Synopsis-

In 2015, nothing happened to implement the Horton Street Bike Boulevard.

In 1998, Emeryville adapted its Bike Plan after years of study and $200,000 spent on it.  In 2013, the City Council agreed to spend $10,000 to study the Bike Plan to figure out how to implement the Horton Street Bike Boulevard required by the Plan.  This $10,000 study is referred to as the 'study of the study'.  The Bike Plan doesn't call for any studies to be done to implement its requirements, it should be noted.  In 2014 City Hall held two community meetings about the study of the study but no action on Horton Street was taken that year or through to the end of 2015.  The 2013 authorized study of the study still hasn't even happened, raising doubts that the 12/31/16 re-post of this story will be any different than today's post.  
Especially disturbing this year is the fact that Emeryville voters elected the progressive City Council majority in 2014 and they have done nothing all year by way of delivering the Horton Street Bike Boulevard even though both Dianne Martinez and Scott Donahue both campaigned as being very pro-bike. 

As a side note: In 2014, City Hall found out another Bike Boulevard, the 45th Street Bike Boulevard is also in violation due to too many cars on that street.  Nothing was done in 2015 to fix that problem either.

Here then is the September 29th, 2012 Tattler story:


Major Traffic Calming Long Past Due For Horton Street

Emeryville's premiere bicycle thoroughfare, the Horton Street Bike Boulevard, has so much high speed traffic that it has become unsafe for bicycling.  So says Alta Planning, a Berkeley based urban bike network design firm that was commissioned by the City of Emeryville to study bicycling in town.  The $200,000 study, now incorporated into Emeryville's Bicycle/Pedestrian Plan and adopted into law by the city council lays waiting, ready to be implemented.
The question is, will it really be implemented or will it languish in some dusty corner at City Hall as so many other expensive studies have done?  Given the city council's baleful history of failing to calm the traffic on Horton Street for bicycle traffic and working to improve the street for vehicle use at the expense of bicycling, it seems likely it will be ignored and will remain a major automobile thoroughfare, unsafe for bicycles and becoming increasingly more so over time.  

Central to the Alta study is a limit on the number of cars that may use Horton Street, set at 3000 vehicles per day, before a mandatory set of traffic calming procedures kicks in.  The idea is that the traffic calming fixes will lower the number of vehicles that use the bike boulevard down below the 3000 maximum.  It should be noted Emeryville's 3000 number earmarked for bike boulevards is larger than any other city in the Bay Area. 

A choker is an example of a 'neck-down'
called for by level 4 traffic calming.
The prescribed traffic calming comes in a series of increasingly interventionist levels, one through five, that reduces traffic volume and speed, the last such level resulting in a total diversion for through traffic.  Each level requires two years to adequately assess its efficacy.  

At this point, Horton Street has already gone through the first three traffic calming levels; these involve street stenciling, signage and intersection "bulb-outs".  Now, since traffic has not subsided on Horton (it's actually increased), it's time for level 4 traffic calming to be implemented according to the Plan.
Level 4 calls for "significant traffic calming", specifically, 'neck downs' or traffic limiters such as 'chokers', designed to act like a one lane bridge permitting only one car through at a time.

Here's what the Bike Plan calls for on Emeryville's bike boulevards:

Level 1 Basic Bicycle Boulevard- signs, pavement markings
Level 2 Enhanced Bicycle Boulevard- way-finding signs, reduced delays at intersections
Level 3 Limited Traffic Calming- intersection bulb-outs
Level 4 Significant Traffic Calming- neck-downs
Level 5 Traffic Diversion


Level 5 calls for diverters: This
is called out only if level 4 doesn't
work after two years.
The problem is the Bike Committee has already twice voted on significant traffic calming for Horton Street in years past.  Both times the city council has overridden the committee's findings.  The last time the committee voted unanimously to add such calming, councilwoman Nora Davis explained her veto to the committee, "I have no problem putting paint on the asphalt [pavement markings]" but anything more dramatic than that would draw a veto from her and consequently also from the council majority.

In the intervening two and a half years since the last council veto shutting down Horton Street traffic calming, the city has commissioned and now encoded the $200,000 Alta study.

While we acknowledge Ms Davis' forthrightness in explaining to the people why they shouldn't expect safe biking routes in town, we call on the rest of the council to abide by the new Bike Plan they have adopted.  The fact that other such documents have been subverted in the past by the council should not serve as a precedent for inaction on Horton Street.  It's never too late to start working towards livability and rational public policy.  Let's make bicycling safe on the Horton Street Bicycle Boulevard.  It's time for a choker on Horton Street.



Saturday, August 1, 2015

Internal Document at City Hall Reveals Clandestine Attempt to Overturn Emeryville Bike Plan

Public Works Department Subverts Bike Plan 

Smoking Gun Document Shows a Department Bent On Torpedoing Settled Bike Policy

A damning internal City Hall document obtained by the Tattler Thursday reveals a rogue Public Works Department attempting to misdirect the newly hired Emeryville City Manager in order to subvert and ratchet back Emeryville's Pedestrian/Bicycle Plan.  The document, a letter from a Public Works employee to City Manager Carolyn Lehr, was sent in response to a public request to conduct a traffic count on 45th Street, a street designated as a bike boulevard, and was meant to assure Ms Lehr no such traffic count is prescribed by the Bike Plan, a patently false claim.

In the letter obtained by a Public Records Request, the employee falsely tells Ms Lehr other than in case of "significant community concern", the only circumstance when the City should conduct traffic counts on 45th Street or any other bike boulevard in Emeryville is when, "significant development occurs on or near that boulevard."  In fact the Bike Plan actually says unequivocally, "[Traffic] counts should be conducted every two years."

Noteworthy is that the Bike Plan prescribes a course of traffic calming action, as is the case for all seven bike boulevards in Emeryville that are found to have an excess amount of traffic, for the 45th Street Bike Boulevard that being a maximum of 1500 vehicle trips per day.  If the street were to be found to have more than this volume of traffic, a regime of traffic calming measures would be automatically initiated as called for by the Bike Plan.  The letter would remove Emeryville's capacity to determine when traffic calming is called for, leaving bicyclists in danger on bike boulevards with gross excess vehicular traffic.

The Bike Plan provides for up to five levels of traffic calming on bike boulevards meant to keep traffic volumes below the maximum allowable for each boulevard.  Traffic calming starts with simple signage and progresses up to level five traffic diverters.  The idea is that on bike boulevards bikes are preferred although cars are allowed so long as the maximum number of cars per day is not reached. Up to two years between each level are called for to study the effects on traffic.
The main north/south bike boulevard in Emeryville, the Horton/Overland Bike Boulevard has been in violation due to excess car traffic for at least ten years and has been a source of friction between the Bike Committee and bike interests versus the Public Works Department.  Decision makers at City Hall have not been able to move Horton Street past level three traffic calming even though the Bike Plan clearly calls for it.  The Horton Street recalcitrance has cast a pall on bicycling as a viable mode of transportation in Emeryville.

Public Works Dept: Increasing Traffic Not Possible
Besides misleading the City Manager about the need for a traffic count on the 45th Street Bike boulevard, the Public Works Department, by falsely presenting the requirement for development on or near bike boulevards to trigger a traffic count, a bizarre and unfounded finding of fact is presented that it is inconceivable that traffic might increase over time in the absence of a development project on or near the street in question.  This premise has been shown to be patently false in the Bay Area over the years.  What has been indicated is an increasing number of vehicles using city streets as the aggregate population in municipalities and the region increases.

Maurice Kaufman, Emeryville's Director of Public Works and the ultimate progenitor of the letter to Ms Lehr it should be noted, has expressed concern over bike boulevards in the past.  He has indicated to the Tattler his job is to make traffic in Emeryville flow more efficiently and he's noted although bikes are not a problem, traffic calming over level three would begin to severely impede the flow of vehicles, something he has said he is duty bound to prevent.
Mr Kaufman is on vacation and unavailable for comment for this story.

The letter to the City Manager omits the Bike Plan's direction for traffic counts every two years on Emeryville's bike boulevards and instead jumps to a section that adds on to that a further requirement to conduct traffic counts when development has occurred.  From the letter dated July 17th:
"...The plan says that the City should collect traffic data when significant development occurs on/near that boulevard or when substantial community concern is brought to the City.  Our last traffic counts on 45th Street were in 2008, and volume did not exceed the goal of 1,500 average daily vehicle trips.  There has been no significant development in the area that would suggest traffic has changed substantially."
From the actual Pedestrian/Bicycle Plan:
Monitoring
As noted in Chapter 4, Section 4.4.3, the City should regularly monitor traffic volumes, and speeds on its bicycle boulevards to determine if they are meeting the goals listed above or not. Counts should be conducted every two years. If a bicycle boulevard goal is not met, the City should consider treatments that will allow the bicycle boulevard to meet goals. If additional treatments are not possible, or if treatments are unlikely to result in conditions that meet the above goals, the City should consider a different type of bicycle facility. Emeryville should collect this data and evaluate each bicycle boulevard in the case of any of the following:
  • Development occurs that is projected to increase motor vehicle volumes on the bicycle boulevard 
  • The Pedestrian and Bicycle Plan is updated 
  • Substantial community concern is brought to the City